![]() | Techniques Guide |
![]() |
Authorisation | ![]() |
Action | ![]() |
Information | ![]() |
Technique | ![]() |
Template |
1. Introduction | ||||||||||||||||||||||||||
This Techniques Guide should be used in conjunction with the other Project Management Guides in this series. The following guides form the complete set.
| ||||||||||||||||||||||||||
1.1 What is included in this Guide? | ||||||||||||||||||||||||||
This guide contains the following information on the major components within the Project Management environment.
| ||||||||||||||||||||||||||
1.2 When should I refer to this guide? | ||||||||||||||||||||||||||
This guide is referenced throughout the Project Management Guides for Level 1 and Level 2 projects. Reference to this guide is indicated by use of this symbol.
![]() | ||||||||||||||||||||||||||
1.3 Other Reference Information | ||||||||||||||||||||||||||
This guide is based on the PRINCE2®; Method, and additional information can be found in the PRINCE2®; reference manual “Managing Successful Projects Using PRINCE2®;”.
You should also seek help and advice from colleagues and mentors who have completed the PRINCE2®; training. The Templates Guide provides detailed information on completing the Management Products when managing projects. You should reference the Template Guide where you see this symbol.![]() | ||||||||||||||||||||||||||
2. Business Case - Development and Lifecycle | ||||||||||||||||||||||||||
The Business Case is described as the justification for an organizational project. It is used to justify the start and continuation of the project. Included in the Business Case are the reasons for undertaking the project, clearly defined benefits, timescales and costs, and a summary of the major risks to the project. | ||||||||||||||||||||||||||
2.1 Business Case Development | ||||||||||||||||||||||||||
![]() The Business Case is developed in outline during the 'Starting up a project' process, and assembled into the Project Brief to support the request to initiate the project. The Project Board will review this information and decide whether the project is worthwhile and viable to start the initiation stage. | ||||||||||||||||||||||||||
![]() |
When writing a Business Case consideration should be given to the information that may already be derived from the early Gateway Review Process steps.
This information and Project Level thinking should be applied to develop a "Project Level" Business Case appropriate in detail to the project that is being started. The Project Manager should consider distinguishing between Project Outputs/Products, The resultant Change/Outcomes and the measurable Benefits to the Business. | |||||||||||||||||||||||||
![]() |
A Benefits Review Plan should also be written at this point defining How and When the measurements of the achievement of the project's benefits can be made. This covers activities during and after the project to measure benefits and the performance of the products in operational life. As the Benefits Review Plan covers activities involved after the project has closed, it is likely to be managed and maintained post-project by Corporate or Programme Management. | |||||||||||||||||||||||||
![]() |
To encourage understanding of the Project and its Scope a Product Breakdown Structure Workshop could be carried out, as well as drafting the Project Product Description.
The Business Case is then refined during the initiation stage, in the 'Initiating a project' process after producing the Project Plan, and assembled as part of the Project Initiation Documentation (PID). It is then submitted to the Project Board as part of the PID for approval at the end stage assessment. For Level 1 projects Start Up and Initiation can be combined as described in 'Managing Level 1 Projects Guide'. Throughout each stage of the project, the Business Case will need to be reviewed, particularly when issues and risks are raised as these may have an impact on the benefits, costs, timescales and existing key risks. As a minimum, the Business Case should be updated by the Project Manager at the end of each management stage as part of the 'Managing a Stage Boundary' process. This will provide the Project Board with the information required to make a decision as to whether or not the projects remains worthwhile and viable. At the end of the project, the Business Case is reviewed to assess the project's performance against its requirements and the likelihood that the outcomes will provide the expected benefits. | |||||||||||||||||||||||||
3. Organisation - Roles and Responsibilities | ||||||||||||||||||||||||||
It is essential to ensure that each role in the Organisation Structure is backed up by a clear set of responsibilities. This section details the standard set of responsibilities which should be reviewed and modified for each project. | ||||||||||||||||||||||||||
3.1 Project Board | ||||||||||||||||||||||||||
The Project Board is accountable to corporate or programme management for the success of the project, and has the authority to direct the project within the remit set by corporate or programme management as documented in the project mandate.
The Project Board is also responsible for the communications between the project management team and stakeholders external to that team (e.g. corporate and programme management). The Project Board membership should be representative of the Stakeholders interests lead by the Executive Role representing the Business and ultimate ownership of the Project. Also the Project Board membership should be able to fulfil the Responsibilities and Competencies listed below. According to the scale, complexity, importance and risk of the project, Project Board members may delegate some Project Assurance tasks to separate individuals. The Project Board may also delegate decisions regarding changes to a Change Authority. General responsibilities During start-up and initiation:
Competencies To be successful, the Project Board should:
| ||||||||||||||||||||||||||
3.2 Executive | ||||||||||||||||||||||||||
The Executive is ultimately responsible for the project, supported by the Senior User and Senior Supplier. The Executive’s role is to ensure that the project is focused throughout its life cycle on achieving its objectives and delivering a product that will achieve the forecast benefits. The Executive has to ensure that the project gives value for money, ensuring a cost-conscious approach to the project, balancing the demands of the business, user and supplier.
Throughout the project, the Executive is responsible for the Business Case. The Project Board is not a democracy controlled by votes. The Executive is the ultimate decision-maker and is supported in the decision-making by the Senior User and Senior Supplier. Responsibilities In addition to the Project Board's collective responsibilities, the Executive will:
| ||||||||||||||||||||||||||
3.3 Senior User | ||||||||||||||||||||||||||
The Senior User is responsible for specifying the needs of those who will use the project's products, for user liaison with the project management team, and for monitoring that the solution will meet those needs within the constraints of the Business Case in terms of quality, functionality and ease of use.
The role represents the interests of all those who will use the project's products (including operations and maintenance), those for whom the products will achieve an objective or those who will use the products to deliver benefits. The Senior User role commits user resources and monitors products against requirements. This role may require more than one person to cover all the user interests. For the sake of effectiveness the role should not be split between too many people. The Senior User(s) specify the benefits and is held to account by demonstrating to corporate or programme management that the forecast benefits that were the basis of project approval are in fact realized. This is likely to involve a commitment beyond the end of the life of the project. Responsibilities In addition to the Project Board's collective responsibilities, the Senior User(s) will:
| ||||||||||||||||||||||||||
3.4 Senior Supplier | ||||||||||||||||||||||||||
The Senior Supplier represents the interests of those designing, developing, facilitating, procuring and implementing the project's products. This role is accountable for the quality of products delivered by the supplier(s) and is responsible for the technical integrity of the project.
If necessary, more than one person may be required to represent the suppliers. Depending on the particular customer/supplier environment, the customer may also wish to appoint an independent person or group to carry out assurance on the supplier's products (for example, if the relationship between the customer and supplier is a commercial one). Responsibilities In addition to the Project Board's collective responsibilities, the Senior Supplier will:
| ||||||||||||||||||||||||||
3.5 Project Manager | ||||||||||||||||||||||||||
The Project Manager has the authority to run the project on a day-to-day basis on behalf of the Project Board within the constraints laid down by them.
The Project Manager's prime responsibility is to ensure that the project produces the required products within the specified tolerances of time, cost, quality, scope, risk and benefits. The Project Manager is also responsible for the project producing a result capable of achieving the benefits defined in the Business Case. It is generally agreed and understood the Project Manager is an internally appointed individual with the requisite skill sets to perform this Role. Specific responsibilities The Project Manager's responsibilities include:
Competencies Different types of project will require different types of project management skills. To be successful, the Project Manager must be able to balance the different aspects of the Project Manager role for a particular project.Key competencies include:
| ||||||||||||||||||||||||||
3.6 Team Manager | ||||||||||||||||||||||||||
The Team Manager’s prime responsibility is to ensure production of those products defined by the Project Manager to an appropriate quality, in a set timescale and at a cost acceptable to the Project Board. The Team Manager reports to, and takes direction from, the Project Manager.
Team Managers need to be considered in line with size, nature and complexity of the work as well as specialist skills required and geographical implications of the project. Team Managers should use Work Packages and Team Plans to capture scope and plan agreements of work that falls under their responsibility. Responsibilities
Competencies Different types of project will require different types of skills from the Team Manager.Key competencies are similar to that of a Project Manager. | ||||||||||||||||||||||||||
3.7 Project Assurance | ||||||||||||||||||||||||||
Project Assurance covers the primary stakeholder interests (business, user and supplier). Project Assurance has to be independent of the Project Manager; therefore the Project Board cannot delegate any of its assurance activities to the Project Manager.
Personnel involved in Project Assurance are also responsible for supporting the Project Manager by giving advice on such things as corporate standards, or correct personnel to involve in quality inspections or reviews. Project Assurance should be involved through out all the processes in the project and as part of its function monitor all aspects of the projects performance and product delivery. They should provide Assurance in line with the required competencies listed below. The Project Assurance role along with the PMO will also assist in ensuring projects follow the PRINCE2® Project Management Method. Responsibilities The implementation of the assurance responsibilities needs to answer the question: what is to be assured? A list of possibilities applicable to the business, user and supplier stakeholder interests would include ensuring that:
Business assurance responsibilities
User assurance responsibilities
Supplier assurance responsibilities
Competencies To be successful, Project Assurance should:
| ||||||||||||||||||||||||||
3.8 Change Authority | ||||||||||||||||||||||||||
The Project Board may delegate authority for approving responses to requests for changes to the Projects Products, Defects, Off-Specifications and Enhancements; to a separate individual or group, called a Change Authority.
The Project Manager could be assigned as the Change Authority for some aspects of the project. | ||||||||||||||||||||||||||
![]() |
When considering the Change Authority it is also useful to Identify the Change Budget; the money allocated to the Change Authority available to be spent on authorised requests for change.
Responsibilities
Competencies The Change Authority should:
Key competencies include:
| |||||||||||||||||||||||||
3.9 Project Management Office (PMO) or Project Support | ||||||||||||||||||||||||||
Project Guidance and Support Whilst it is considered that Project Managers will manage and administer projects themselves they are not without guidance and support. The Project Management Office Role is recognised for providing guidance and support in areas that cross over many projects. These areas fundamentally include Project Planning, Risk Management, Configuration Management and Change Control. This Role also has Responsibility for this Project Management Guide and its contents. Summary of PMO Responsibilities
Competencies Key competencies include:
| ||||||||||||||||||||||||||
4. Quality | ||||||||||||||||||||||||||
The approach to quality is systematic in that it requires the Project Manager to plan how quality will be achieved.
Quality Planning begins with establishing the acceptance criteriafor the project during Start Up, and the Products are identified and defined using the Product based planning technique during Initiating and Stage Boundaries. The development and quality management of these products should then be planned in the appropriate level of plan, whether it is at project, stage or team level. The level of quality applied to the project will depend on its size and nature. Delivery of products that meet quality criteria is paramount to the success of any project, which means that quality management needs to be applied correctly. | ||||||||||||||||||||||||||
During Starting Up a Project a common understanding of quality expectations from the Customer needs to be established, along with measurable success criteria for the project; Customer Quality Expectations (User Requirements) | ||||||||||||||||||||||||||
![]() |
Information from the Customer Quality Expectations and acceptance criteria will be input to the Project Product Description so that a clear understanding of the overall project's requirements and criteria are documented and agreed, which in turn will feed into the development of the Quality Management Strategy during the Initiation Stage. | |||||||||||||||||||||||||
4.1 Project Product Description | ||||||||||||||||||||||||||
![]() |
The Project Product Description will be reviewed at the end of each stage to check for any changes required. It will also be used when closing the project to ensure that the project has delivered what it set out to do and aid in Customer Acceptance. | |||||||||||||||||||||||||
4.2 Product Descriptions | ||||||||||||||||||||||||||
![]() |
Project level products will be identified during Initiating, and therefore Product Descriptions for these are needed to define the products and their Quality Criteria and checking methods.
These Product Descriptions will form part of the Stage Plan, and will be baselined when the relevant Stage Plan is approved by the Project Board. Details of the quality criteria, quality checking methods and skills required are included in the Product Descriptions, giving clear definition of how the product should be checked. | |||||||||||||||||||||||||
4.3 Quality Management Strategy | ||||||||||||||||||||||||||
![]() |
During Initiating a Project, the Quality Management Strategy is created to define the quality techniques and standards to be applied. The Quality Management Strategy contains information on quality responsibilities for achieving the required quality levels, the types of quality checking methods to be used, and how recording and reporting of quality will be carried out during the project.
The Quality Management Strategy is approved by the Project Board as part of the PID, and is then reviewed during each stage to reference the quality management procedures and methods. At the end of each stage, and at the end of the project, it is used to define how quality statistics are reported. | |||||||||||||||||||||||||
4.4 Quality Control | ||||||||||||||||||||||||||
Quality Control is the practice of implementing, monitoring and recording the quality activities that have been planned to ensure that products are assessed for conformity to their quality criteria. | ||||||||||||||||||||||||||
![]() |
The Quality Registeris also created during Initiating and will be used to record the planned dates for quality control and will record the activities and results of the quality reviews and checks, this information is then used for input to Highlight Reports, and then summarized in the End Stage Report. | |||||||||||||||||||||||||
4.4.1 Quality Review Technique | ||||||||||||||||||||||||||
The Quality Review Technique tests that each product delivered meets the criteria of the requirement. These quality criteria will have been recorded in the Product Description during the planning stage.
![]() | ||||||||||||||||||||||||||
4.4.2 Types of Quality Reviews | ||||||||||||||||||||||||||
Quality Reviews can be either formal, for example a scheduled meeting, or informal. The selection of the type of quality review is the responsibility of the Project Manager, endorsed by the Project Board when approving a plan at the End Stage Assessment.
An informal Quality Review may take many forms.
| ||||||||||||||||||||||||||
4.4.3 The Quality Review Steps | ||||||||||||||||||||||||||
Step 1 - Review Preparation The objective of this step is to examine the Product under review against its Product Description and to create a Question List of queries, possible errors, and topics that warrant re-examination.Step 2 - The Review Meeting Agenda The objective of the Review Meeting is to agree the list of queries, observations and errors in the Product. It is not necessary to reconcile these errors at the meeting; but rather to agree that a particular area needs re-examination or re-work. Any follow-up action required should be recorded a QR Action List, and the Project Manager notified of these. If it is agreed that the product meets its criteria, then this can be recorded in the Quality Register (Test Director).Step 3 - Review Follow-up The objective of the Follow-up step is to ensure that all items identified on the QR Follow-Up Action List are dealt with and signed off, and the Project Manager notified of the review results. | ||||||||||||||||||||||||||
4.5 Project Assurance & Quality Assurance | ||||||||||||||||||||||||||
It is important to understand the differences between the roles of Quality Assurance and Project Assurance.
Quality Assurance creates and maintains the Quality Management System, ensuring that corporate standards are applied to activities that occur in appropriate departments of an organization, whether those activities are within a project or not. Project Assurance on the other hand is a role that ensures the project management approaches and standards are adhered to within the project. There is some cross-over when corporate standards apply to projects. These should be defined in the Project's Quality Management Strategy. Quality Assurance has the responsibility to check that these standards are applied correctly within the project, while Project Assurance is responsible for ensuring that the corporate standards are defined in the Quality Management Strategy. | ||||||||||||||||||||||||||
5. Plans | ||||||||||||||||||||||||||
A plan provides information on how the products, timescales, costs and quality can be met, using the available resources within the given constraints. There will be a number of elements that make up a plan, including the products to be produced; the activities needed to create those products; the resources, time and budget needed for all activities (plus tolerances); dependencies between activities; planning assumptions; inherent risks and the points at which progress will be monitored and controlled. Plans will be need to be written at the right level of detail, and at the appropriate time. For instance, planning the entire project in detail during the initiation stage would not be desirable or even possible. The length of time we can plan ahead in detail with some accuracy is known as the planning horizon. Plans should therefore be prepared at different levels of scope and detail. Detailed Stage Plans should be prepared near the end of the current stage to help counter the planning horizon issue. The planning steps will primarily take place during initiation when planning the project, and towards the end of each management stage when producing Stage Plans. If requested, Exception Plans may be produced to recover a project or stage from exceeding tolerances. The Exception Plan is seen to be on the same level as the Stage Plan, and is not used for recovering Work Package exceptions. Exception Plans would also be produced use the planning steps. Optional Team Plans may also be needed, and could be created in parallel with the Stage Plan. If a Team Manager forecasts that the Work Package may exceed tolerances, they will notify the Project Manager by raising an issue which then if need be could become an exception. Additional guidance on some of the planning techniques used can be found within this guide. |
||||||||||||||||||||||||||
5.1 Planning Procedure | ||||||||||||||||||||||||||
![]() |
A plan is made up of many pieces of information, and therefore requires several different techniques to complete it. A template for a typical plan is in the Templates Guide. The table below shows each step required for creating the full plan. These steps of planning are iterative and are used each time a plan is created. In order to develop consistent Plans/ Schedules the following planning steps should be considered:
| |||||||||||||||||||||||||
5.2 Product Based Planning Steps | ||||||||||||||||||||||||||
Product Based Planning is the planning technique that is unique to the PRINCE2 method. All levels of project should use the Product Based Planning technique.
The key benefit to having a product based approach to planning is that its initial focus is on deliverables, rather that activity. This will help you better understand the products that need creating. There are four main steps to Product Based Planning:
| ||||||||||||||||||||||||||
5.2.1 Product Breakdown Structure | ||||||||||||||||||||||||||
The Product Breakdown Structure (PBS) creates a list of Products to be produced during the project. The standard technique is to identify the end product, and then break this down to show the products that are required to be developed.
Example of a Product Breakdown Structure ![]() The format of the PBS is often that of a diagram, where the products are broken down using a hierarchical approach, although you might prefer a more textual approach using Bullet Points for example. Some projects may require a workshop involving many people; for others the Project Manager may be able to complete this alone. Either way the outcome is the same – a list of products that need to be developed. At the beginning of Level 2 projects, it is sensible to plan the project at high-level, identifying the main products first when creating your Project Plan. More detailed plans can be created for each stage as the project progresses. The resultant list should be critically reviewed with the Project Management Team in the light of what is known about the proposed project, to produce an agreed list of the Products to be produced. This is known as a Product Breakdown Structure and contains a list of the Specialist Products and Management Products associated with the project. | ||||||||||||||||||||||||||
5.2.2 Product Descriptions | ||||||||||||||||||||||||||
![]() |
Product Descriptions form a significant part of the Quality arrangements for the project and are fundamental to its successful outcome. For these reasons Product Descriptions must not, in any circumstances be omitted from any PRINCE2®; controlled project.
Each Product identified in your PBS requires a Product Description. Content and advice on Product Descriptions can be found in the Templates Guide. Product Descriptions are key to ensuring the quality of products, and therefore need careful consideration when writing them. The Quality section in this Techniques Guide explains how Product Descriptions are used to check that a product is “fit for purpose”. It is advisable to read the Quality chapter prior to writing the Product Descriptions to give yourself an understanding of how the information is used. | |||||||||||||||||||||||||
5.2.3 Product Flow Diagram | ||||||||||||||||||||||||||
This is the final step of Product Based Planning. The Product Flow Diagram (PFD) is a way of sequencing the order of development of the products. There may be a number of different paths in the PFD, all flowing into the final deliverable.
Example of a Product Flow Diagram
| ||||||||||||||||||||||||||
5.4 Identify Activities and Dependencies | ||||||||||||||||||||||||||
The reason for creating the PFD is to assist when you come to identifying activities. As opposed to starting with a blank canvas, your start point will be the PFD which should help you answer the question “what needs to be done to complete this product?” Example of the PFD with activities added Product Based Planning is a technique to assist with future steps of planning. It does not provide a plan itself. As a result of completing these steps, you will now have a list of products (from the PBS) and a list of activities (from the PFD). This information can now be used in the next step of planning – estimating and scheduling. | ||||||||||||||||||||||||||
5.4 Prepare Estimates | ||||||||||||||||||||||||||
Using the activities identified on the Product Flow Diagram, you should now make an assessment of the effort required to carry out the activities, and resources and skill types required. There are many different ways of estimating including:
| ||||||||||||||||||||||||||
5.5 Prepare the Schedule | ||||||||||||||||||||||||||
You should now have the following:
A simple Logic Diagram The above diagram is a simple “Logic Diagram” which shows the dependencies of each activity. Use this technique to place the activities in sequence. This will help to identify which activities are dependant on others. Using the Logic Diagram, you can now apply the time estimates. This is easily done using a software tool such as MS Project. There is a manual technique for completing this known as the “Programme Evaluation Review Technique”. The PRINCE2®; Manual explains this technique. When you have applied the estimates, you should have a better understanding of the total timeline of the plan, and a clear indication of what and when things will happen. This is usually presented in graphical form known as a Bar Chart or Gantt Chart (see below). Example of a Bar Chart | ||||||||||||||||||||||||||
5.6 Completing the Plan | ||||||||||||||||||||||||||
You will now have most of the information necessary to complete the plan. The complete set of planning elements are:
Throughout the planning approach, the Project Manager will need to analyse the risks associated with the plan. This might include risks that have already been identified on the Risk Register, or new risks that have materialized as a result of creating the plan. Analysing risks during planning is iterative and may lead to previous steps of planning being revisited in order to make changes to the plan to lessen or remove the risks. The final step of planning is to summarise the plan. Known as the Plan Text, it should include an explanation of the assumptions that have been made when creating the plan and the key risks that are associated with the plan. | ||||||||||||||||||||||||||
5.7 Summary | ||||||||||||||||||||||||||
During the planning stage of all projects you will be using many other aspects of this guide:
In addition to the above list, you should always monitor the Business Case as costs will undoubtedly be affected by the work that is planned. | ||||||||||||||||||||||||||
6. Risk Management | ||||||||||||||||||||||||||
Throughout any project it is important to ensure that risks are identified, understood, tracked and managed. This will help prevent, or at least limit the impact of unforeseen circumstances. A risk is defined as an uncertain event that will have an effect on the achievement of objectives if it occurs. People often confuse Risks and Issues, so it is important to understand the differences: Risk is uncertainty, for example something that might happen. An Issue is a certainty, for example an event that has, or will definitely occur. | ||||||||||||||||||||||||||
6.1 Risk Management Strategy | ||||||||||||||||||||||||||
![]() |
The Risk Management Strategy is created in the initiation stage to establish the risk management procedures, techniques and standards that are to be applied to the project. Some organizations have these procedures as standards, which means that they can be integrated into the Risk Management Strategy quite easily.
This strategy is defined in the 'Initiating a project' process so that there is a clear understanding of the risk management procedures for the remainder of the project. It is then used throughout each stage of the project so that there is a consistent way of managing risk.
A Risk Budget is sum of money that is put aside specifically for funding risk responses. The Risk Budget should be defined during the Initiation Stage and recorded in the Risk Management Strategy. The overall project's risk exposure will help determine the value of the Risk Budget, but it is advisable that provision should also be made for risks that are identified later on in the project. At the end of each management stage, the Risk Management Strategy should be used to ensure that risks are being managed in line with the defined strategy, as this is a key time for assessing new risks, as well as those already on the Risk Register. Finally, the Risk Management Strategy is used during the 'Closing a Project' process to ensure that outstanding risks on the Risk Register are handled in the appropriate way when handing over products and completing follow-on action recommendations. | |||||||||||||||||||||||||
6.2 Risk Management Technique | ||||||||||||||||||||||||||
Risk Management is the use of a set of procedures to identify and manage risks summarized in the steps of the Risk Management cycle below :![]() | ||||||||||||||||||||||||||
6.2.1 Identify | ||||||||||||||||||||||||||
Identify' is broken into two parts of 'Identify Context' and 'Identify Risks'.
The 'Identify Context' step is used to obtain information about the project in order to understand the specific objectives that are at risk. This information is then used to formulate the Risk Management Strategy during the IP process. The 'Identify Risks' step is to recognise the specific threats and opportunities that may affect the project's objectives. Each of these needs to be captured on the Risk Register. Risks can be identified using the following approaches.
It is also important to understand what the actual risk is, as it is easy to confuse the cause of a risk with the risk itself. For example, a Risk Cause might be that it has been raining heavily. This presents a Risk Event that a river running through a farmer's field might overflow, giving a Risk Effect of severely damaging the farmer's crop. | ||||||||||||||||||||||||||
![]() |
All risks should be recorded in the Risk Register. In some small projects it may be acceptable to record risks as part of the PID rather than in a separate Risk Register. A template for a Risk Register is in the Templates Guide.
The Risk Register is used to capture information on risks and includes details of the probability and impact of the risk, the people assigned to manage the risk, the risk category, and the responses identified to resolve the risk. The information on each risk is updated regularly to record any changes in status of each risk. The Risk Register should reflect the needs of the project, and can be managed in many different ways. In some projects there may be a need to use separate Risk Registers for the customer and supplier environments - this might be for commercial or technical reasons. There may also be a need for joint Risk Registers that cover a number of technical teams. However the Risk Register is managed, it needs to be clear that the Project Manager is ultimately responsible for identifying and managing risks throughout the project. Produced in the Initiation Stage, the Risk Register is created in parallel to defining the Risk Management Strategy. It is worth remembering though that some risks might have already been identified during the Start Up. These risks will have been recorded in the Daily Log and would now be transferred onto the Risk Register. At the end of the initiation stage a summary of the risks will be entered into the End Stage Report, and these will be reviewed and approved by the Project Board. Throughout each stage of the project the Project Manager will review the Risk Register and update it with details of new risks, as well as changes to existing risks. As issues are raised, the Risk Register will need reviewing and updating to reflect any impacts to risks. At the end of each management stage, a summary of risks is entered into the End Stage Report in preparation for the Project Board approval. At the end of the project, the Risk Register is used to transfer details of any risks to operations and maintenance teams as part of handing over products in the CP process. Risk Categories The following categories can be used as a starting point for identifying your organisation's main areas of risk in relation to projects or programmes. Strategic/commercial risks
| |||||||||||||||||||||||||
6.2.2 Assess / Estimate/ Evaluate | ||||||||||||||||||||||||||
The second step in the Risk Management procedure is to Assess the risks that are identified. This element is split into two steps - Estimate and Evaluate. The Estimate step is concerned with estimating the probability and impact of each risk; when the risk is likely to occur (or proximity), and how the impact of risks may change over the life of the project.
The Evaluate step is concerned with understanding the net effect of all identified risks to assess the overall effect of these on the project risk tolerance. This step gives the Project Manager the foresight to escalate to the Project Board if necessary. All identified risks need be assessed to establish their importance using the following two headings:
You should assess how the risk will affect the progression of the plan. Risks that require immediate action should be dealt with as an Issue (see the 'Change' section of this Techniques Guide). | ||||||||||||||||||||||||||
6.2.3 Plan Responses | ||||||||||||||||||||||||||
The third step in the Risk Management procedure is 'Plan'. This is where specific responses to remove or reduce threats are identified and evaluated. When considering any risk responses, there needs to be an evaluation of the impact of carrying out a response, balanced against the cost and impact of implementing the response.
If you need to put into place actions that will help prevent or reduce the impact or probability of the risk, then this should be planned and carried out, with authorisation sought from the Project Board. The following Risk Responses should be used.
When looking at actions to mitigate risks, the total cost of mitigation should not be more that the potential value of the impact. For instance, it is not worth spending £10,000 to mitigate a risk that will only impact the project of a cost of £5,000. However, there may be other impacts to consider. During this step, a Risk Owner and a Risk Actionee should be assigned to manage the risk. The Risk Owner is responsible for ensuring the responses are carried out, as well as monitoring that the responses are having the desired effect on the risk. The Risk Actionee is responsible for carrying out the specific risk response actions. Quite often these two roles will be carried out by the same person and can be the Project Manager, a team resource, a member of the Project Board, or any other Stakeholder. | ||||||||||||||||||||||||||
6.2.4 Implement / Communicate | ||||||||||||||||||||||||||
The fourth step of the Risk Management procedure is 'Implement'. This step ensures that the responses that are identified and planned in the previous step are actually carried out, and that these responses are having the desired effect on the risk.
The Communicate step is carried out continually to keep both the Project Management Team and external stakeholders informed. When handling such communication, it is important to use the Communication Management Strategy to ensure that the information being provided is in line with what has been agreed in the PID. Throughout the life of the Project, risks will come and go. Should a risk happen, then the details should be transferred to an Issue Report and the Issue Register. As new risks are identified and other risks diminish, you will need to keep the information on risks up-to-date by updating the Risk Register. The volatile nature of risks means that the Risk Register should be monitored on a regular basis. Details of risks should be communicated to project team members using the following management reports: Consider the numerous other communication methods such as bulletins, notice boards, dashboards, discussion threads, briefings etc. Refer to the Communication Management Strategy for the most appropriate method. | ||||||||||||||||||||||||||
7. Change | ||||||||||||||||||||||||||
More often than not changes lead to higher costs or more time to deliver the products. Without change control, changes will almost certainly lead to products being delivered that do not meet the customer's criteria. Therefore every project needs a systematic approach to handling change. To ensure products are safeguarded, a Configuration Management procedure is also required. This will record information on all products, including identifiers and versions, copy holders, historical information and status. It also controls the products by triggering the change control procedure when necessary. Where it is anticipated that there could be many changes during the project, the Project Board might look to appoint a Change Authority to authorize changes on its behalf. It is worth bearing in mind that the Change Authority role can be allocated to more than one person. For example, the Project Manager could be given authority for changes relating to Work Packages, while somebody in a Project Assurance role could decide on Stage or even Project level changes. The Project Board can also put restrictions on the number of changes to any products, or the value of the changes in any one stage. A Change Budget is a sum of money that can be used by the Change Authority to fund changes. Details of the Change Authority and Change Budget should be established during the Initiation Stage and approved by the Project Board as part of approving the PID. There are three types of Change or Issue that will be used by the Project Manager : A Request for Change will usually come from the Customer or User environment and will affect a change to the agreed acceptance criteria or Product Description (ARQ's and ECN's). A Request for Change could also request a change to the scope of the project too, like an additional product. An Off-Specification is a product that has failed to meet some criteria during quality activity. It could also be a product that should have been delivered, but has not been. Off-Specifications are typically raised by the Supplier or Team Manager, a Reviewer or Chair of the Quality Review Team, or by Project Assurance. All other Issues are categorized as general problems or concerns. If an Issue is categorized as a concern (i.e. a potential risk), and is considered formal, then it will be transferred to the Risk Register and analyzed using the Risk Management procedure. All other Issues will be handled using the Issue and Change Control Procedure. Issues can originate from anybody - the Project Board, the Project Manager, teams, or anybody else from any area within the authority or outside the authority. Issues may relate to anything about the project, and can be of any nature including
| ||||||||||||||||||||||||||
7.1 Handling Issues | ||||||||||||||||||||||||||
![]() The standard approach for dealing with Issues is outlined below: | ||||||||||||||||||||||||||
![]() |
An Issue Report is created to formalise information about an Issue that needs to be managed formally. It will be created initially to record known information, and then updated after impact analysis has been carried out on the Issue to include details of the effect the Issue has on stage and project costs, time and risks, and impacts on other products. It will also contain information on the recommended actions required to resolve the Issue, and the decision that has been made. The Issue Register provides a summary of all formal Issues that are being managed during the Project. Information from the Issue Reports will be used to generate a register that provides information on all Issues 'at a glance'. This helps the Project Manager to easily monitor all Issues. | |||||||||||||||||||||||||
7.2 Configuration Management | ||||||||||||||||||||||||||
![]() |
Configuration Management ensures that the products that the project creates are managed and controlled. It also extends to supporting the use of the product after the project has closed, so needs to address both individual projects and the organisation as a whole. It is a technical and administrative activity concerning the creation, maintenance and controlled change of configuration throughout the life of a product
The Configuration Management Strategy is created by the Project Manager during the Initiation Stage and defines the project's procedures for Configuration Management, Issues and Change. It will also define the responsibilities for these procedures, as well as reporting mechanisms, tools and techniques. The Configuration Management Strategy forms part of the Project Initiation Documentation, and is therefore approved in DP by the Project Board. It is reviewed throughout the CS process when the Project Manager has issues to deal with. It will also be used when creating Work Packages so that the procedures can be written into these. The Project Manager will also need to refer to the procedures during the CP process when preparing for handing over products to the operations and maintenance teams. Configuration Item Records (or C.I.R.s) are created for each product that is identified. They provide a full set of information for each product including the product names and version, who owns the product and who holds copies, which is important when needing to ensure that everyone is referring to the correct version. A Product Status Account can be used to summarize the information that is held in the Configuration Item Records. By managing the information this way the Project Manager will be able to produce a report on a set of products, whether it be for the entire Project, a particular Stage, or for a set of products being delivered by a specific team. Configuration Management therefore is basically a record of all products produced within the Project. This includes details of the specialist products and Management Products. The five basic functions of Configuration Management are:
Decisions need to be made during project initiation to:
| |||||||||||||||||||||||||
7.2.1 Configuration Management Techniques | ||||||||||||||||||||||||||
Configuration Management (CM) provides techniques and procedures to perform the following functions:
Overall responsibility for Configuration Management on individual projects will be exercised by each Project Manager. PRINCE2®; describes configuration management as “Product Control”. This is because it is the Configuration Management system which ensures that all products which have been approved by the Performance Board, or have been signed off at Quality Review will become baselined by changing the status to “Approved”. This effectively protects those products from changes by ensuring that the formal change control method is triggered when changes are required. | ||||||||||||||||||||||||||
7.3 Filing Structure | ||||||||||||||||||||||||||
The suggested documentation management or filing structure is based on three different types of file:
| ||||||||||||||||||||||||||
7.3.1 Project Filing Structure | ||||||||||||||||||||||||||
Each project should only have one Project File.
| ||||||||||||||||||||||||||
7.3.2 Stage File(s) | ||||||||||||||||||||||||||
A Stage File would exist for each stage of the project
| ||||||||||||||||||||||||||
7.3.3 Quality file | ||||||||||||||||||||||||||
![]() |
The objective of a quality file is to permit an audit, at any time, of the quality work being done and to confirm adherence to quality standards. There is one quality file that runs through the whole project and is not divided into stages. It has the following major divisions:
| |||||||||||||||||||||||||
7.3.4 Physical Filing Considerations | ||||||||||||||||||||||||||
The files themselves may take on a variety of guises from a consolidated four-post binder to document management systems and configuration management libraries.
You should seek assistance from the Project Management Office for guidance on this. | ||||||||||||||||||||||||||
8. Progress | ||||||||||||||||||||||||||
A key objective of project management is to exercise control over the progress that the project is making in order to provide management with accurate and timely decision support information. Decision makers cannot make informed decisions unless they are presented with up to date facts. Knowing what has been achieved against what has been planned is vital.
Controls such as formality of meetings and reporting for the project should be established during the project initiation stage. The formality and type of controls to be used should be discussed with the Project Board. When deciding on the types and levels of controls to be used on the project, be sure to consider the costs of high formal controls against the risks of lower level informal controls. The result may be a balance which can be decided and approved by the Project Board. As part of the 'Controlling a Stage' process the Project Manager will regularly review the progress of the stage and update the Stage Plan with actual progress achieved. Information from a number of Management Products is used for reviewing progress. When reviewing progress, the Project Manager will look at what has been achieved to date, and look at how this affects the remainder of the stage and project. | ||||||||||||||||||||||||||
8.1 Highlight Report | ||||||||||||||||||||||||||
![]() |
Highlight Reports should be used to provide information to the Project Board on progress of the project, and of each management stage as it progresses. Highlight Reports should be completed on a regular basis, as agreed with the Project Board. As a guide, these will be weekly on Level 1 Projects, monthly for Level 2 Projects (although the Project Board may indicate that the report be more, or less, frequent). | |||||||||||||||||||||||||
8.2 End Stage Report | ||||||||||||||||||||||||||
![]() |
At the end of each Management Stage (whether or not a lower-level plan has been created) you will need to produce an End Stage Report that confirms to the Project Board that all the work planned and approved for that Management Stage is completed, and that all the Products are finished and of the required quality.
The Project Board will also require a statement of actual cost and duration against the approved plan, and any actual or proposed change in the organisation. A vital element is an up-dated Business Case and Risk Analysis. This document must be kept short and to the point. The up-dated Project Plan and Management Stage Plan must be available to the Project Board and, if deemed useful, a Management Stage Plan for the next stage of the work must accompany the Report. |
|||||||||||||||||||||||||
8.3 Tolerances and Variance Reporting | ||||||||||||||||||||||||||
A key aspect of progress monitoring and control is knowing when things are still on target; within plan; within tolerance. Tolerance is the permissible deviation of an approved plan, without needing to report that deviation to the higher level. This is commonly known as "management-by-exception". The Project Manager should be in complete control of the project - enabling the Project Board to take a "back seat". All projects levels are subject to Tolerance. Tolerance of +/- a percentage should be applied to all projects. The Project Board may vary tolerances and add additional tolerances, perhaps on specific packages of work or elements. Practically anything that can be measured can have Tolerance applied to it (e.g. benefits, risks, quality, scope, time and cost). All Level 2 projects and some Level 1 projects will have additional Tolerances applied to them in order to give the Project Board confidence in allowing the Project Manager to get on with managing the project. For example, if a plan is approved with a predicted duration of 20 weeks and at an estimated cost of £50,000, using the standard tolerance of +5% (1 week) duration and +5% on cost, then the Project Manager can continue with the project without reference back to the Project Board, provided the predicted duration does not stretch further than 11 weeks, and the predicted cost does not exceed £52,500 (£50,000 + 5%). Any deviation beyond these tolerance figures must be reported to the Project Board immediately, using an Exception Report. |
||||||||||||||||||||||||||
8.4 Exception Report | ||||||||||||||||||||||||||
![]() |
The purpose of the Exception Report is to alert the Project Board that a deviation from the approved plan has been detected and that tolerances are forecast to be exceeded. During each stage, if there is a forecast that the agreed tolerances will be exceeded, then the Project Board will rely on Exception Report being escalated by the Project Manager which will trigger them into action. It is created by the Project Manager in the CS process includes details of what has caused the deviation, the options available for recovery, the impact of each option on the Business Case, Risks and tolerances, and a recommendation from the Project Manager on what is considered to be the best of the available options.
The Project Board may meet to consider an Exception Report, but a formal meeting is not always necessary. More likely, the Project Board will review the situation informally, by telephone or e-mail, and then give its response. |
|||||||||||||||||||||||||
8.5 Work Package | ||||||||||||||||||||||||||
![]() |
If the project is large and complex then the Project Manager will also use controls for progressing each stage of the project. These include Work Packages which are used to authorize work to the Team Managers; Checkpoint Reports sent from the Team Manager to the Project Manager that give a summary of the work of the teams; registers to summarize the Issues, Risks and Quality activities, and a Daily Log to record informal events. The Lessons Log is also used to capture procedures and techniques that can assist with future projects.
The Work Package is used to delegate work from the Project Manager in the CS process, to individual team members or Team Managers operating in the MP process. The Work Package could take the form of a legally binding contract with an external supplier, or could take the form of a discussion or briefing; especially true where the creation or modification of a Product is being carried out by internal staff from the customer's own organisation. The way in which it is authorized to the teams will be in keeping with the formality of the Work Package. The Work Package will contain details of the work to be completed, including timescales and costs, quality procedures, reporting requirements and how problems should be handled. It is advisable to include a copy of all Product Descriptions which includes the Quality Criteria that relate to the Work Package. |
|||||||||||||||||||||||||
8.6 Checkpoint Report | ||||||||||||||||||||||||||
![]() |
Checkpoint Reports are a time-driven control created by the Team Manager in the 'Managing Product Delivery' (or MP) process. They provide information for the Project Manager on the progress of a Work Package at a frequency that is defined in the Work Package.
The Team Manager will use the Team Plan, Issue Register, Risk Register and Quality Register to create the Checkpoint Report. It is also useful to have a checkpoint meeting with the teams prior to sending the Checkpoint Report so that any other useful information can be included. On receiving the Checkpoint Report, the Project Manager will update the Stage Plan as part of Reviewing Progress. |
|||||||||||||||||||||||||
9. Project Management Glossary | ||||||||||||||||||||||||||
accept (risk response) A risk response to a threat where a conscious and deliberate decision is taken to retain the threat, having discerned that it is more economical to do so than to attempt a risk response action. The threat should continue to be monitored to ensure that it remains tolerable. acceptanceThe formal act of acknowledging that the project has met agreed acceptance criteriaand thereby met the requirements of its stakeholders. acceptance criteriaA prioritized list of criteria that the project product must meet before the customer will accept it, i.e. measurable definitions of the attributes required for the set of products to be acceptable to key stakeholders. activityA process, function or task that occurs over time, has recognizable results and is managed. It is usually defined as part of a process or plan. ad hoc directionAdvice and guidance passed from the Project Board to the Project Manager. agile methodsPrincipally, software development methods that apply the project approach of using short time-boxed iterations where products are incrementally developed. PRINCE2 is compatible with agile principles. approvalThe formal confirmation that a product is complete and meets its requirements (less any concessions) as defined by its Product Description. approverThe person or group (e.g. a Project Board) who is identified as qualified and authorized to approve a (management or specialist) product as being complete and fit for purpose. assumptionA statement that is taken as being true for the purposes of planning, but which could change later. An assumption is made where some facts are not yet known or decided, and is usually reserved for matters of such significance that, if they change or turn out not to be true, there will need to be considerable replanning. assuranceAll the systematic actions necessary to provide confidence that the target (system, process, organization, programme, project, outcome, benefit, capability, product output, deliverable) is appropriate. Appropriateness might be defined subjectively or objectively in different circumstances. The implication is that assurance will have a level of independence from that which is being assured. See also 'Project Assurance' and 'quality assurance'. authorityThe right to allocate resources and make decisions (applies to project, stage and team levels). authorizationThe point at which an authority is granted. avoid (risk response)A risk response to a threat where the threat either can no longer have an impact or can no longer happen. baselineReference levels against which an entity is monitored and controlled. baseline management productA type of management product that defines aspects of the project and, once approved, is subject to change control. benefitThe measurable improvement resulting from an outcome perceived as an advantage by one or more stakeholders. Benefits Review PlanA plan that defines how and when a measurement of the achievement of the project's benefits can be made. If the project is being managed within a programme, this information may be created and maintained at the programme level. benefits toleranceThe permissible deviation in the expected benefit that is allowed before the deviation needs to be escalated to the next level of management. Benefits tolerance is documented in the Business Case. See also 'tolerance'. Business CaseThe justification for an organizational activity (project), which typically contains costs, benefits, risks and timescales, and against which continuing viability is tested. centre of excellenceA corporate coordinating function for portfolios, programmes and projects providing standards, consistency of methods and processes, knowledge management, assurance and training. Change AuthorityA person or group to which the Project Board may delegate responsibility for the consideration of requests for change or offspecifications. The Change Authority may be given a change budget and can approve changes within that budget. change budgetThe money allocated to the Change Authority available to be spent on authorized requests for change. change controlThe procedure that ensures that all changes that may affect the project's agreed objectives are identified, assessed and either approved, rejected or deferred. checkpointA team-level, time-driven review of progress. Checkpoint ReportA progress report of the information gathered at a checkpoint, which is given by a team to the Project Manager and which provides reporting data as defined in the Work Package. closure notificationAdvice from the Project Board to inform all stakeholders and the host sites that the project resources can be disbanded and support services, such as space, equipment and access, demobilized. It should indicate a closure date for costs to be charged to the project. closure recommendationA recommendation prepared by the Project Manager for the Project Board to send as a project closure notification when the board is satisfied that the project can be closed. Communication Management StrategyA description of the means and frequency of communication between the project and the project's stakeholders. concessionAn off-specification that is accepted by the Project Board without corrective action. configuration itemAn entity that is subject to configuration management. The entity may be a component of a product, a product, or a set of products in a release. Configuration Item RecordA record that describes the status, version and variant of a configuration item, and any details of important relationships between them. configuration managementTechnical and administrative activities concerned with the creation, maintenance and controlled change of configuration throughout the life of a product. Configuration Management StrategyA description of how and by whom the project's products will be controlled and protected. configuration management systemThe set of processes, tools and databases that are used to manage configuration data. Typically, a project will use the configuration management system of either the customer or supplier organization. constraintsThe restrictions or limitations that the project is bound by. contingencySomething that is held in reserve typically to handle time and cost variances, or risks. PRINCE2 does not advocate the use of contingency because estimating variances are managed by setting tolerances, and risks are managed through appropriate risk responses (including the fallback response that is contingent on the risk occurring). corporate or programme standardsThese are over-arching standards that the project must adhere to. They will influence the four project strategies (Communication Management Strategy, Configuration Management Strategy, Quality Management Strategy and Risk Management Strategy) and the project controls. corrective actionA set of actions to resolve a threat to a plan's tolerances or a defect in a product. cost toleranceThe permissible deviation in a plan's cost that is allowed before the deviation needs to be escalated to the next level of management. Cost tolerance is documented in the respective plan. See also 'tolerance'. customerThe person or group who commissioned the work and will benefit from the end results. customer's quality expectationsA statement about the quality expected from the project product, captured in the Project Product Description. Daily LogUsed to record problems/concerns that can be handled by the Project Manager informally. deliverableSee 'output'. dependencies (plan)The relationship between products or activities. For example, the development of Product C cannot start until Products A and B have been completed. Dependencies can be internal or external. Internal dependencies are those under the control of the Project Manager. External dependencies are those outside the control of the Project Manager - for example, the delivery of a product required by this project from another project. dis-benefitAn outcome that is perceived as negative by one or more stakeholders. It is an actual consequence of an activity whereas, by definition, a risk has some uncertainty about whether it will materialize. DSDM AternAn agile project delivery framework developed and owned by the DSDM consortium. Atern uses a time-boxed and iterative approach to product development and is compatible with PRINCE2. embedding (PRINCE2)What an organization needs to do to adopt PRINCE2 as its corporate project management method. See also, in contrast, 'tailoring', which defines what a project needs to do to apply the method to a specific project environment. End Project ReportA report given by the Project Manager to the Project Board, that confirms the handover of all products and provides an updated Business Case and an assessment of how well the project has done against the original Project Initiation Documentation. end stage assessmentThe review by the Project Board and Project Manager of the End Stage Report to decide whether to approve the next Stage Plan. According to the size and criticality of the project, the review may be formal or informal. The authority to proceed should be documented as a formal record. End Stage ReportA report given by the Project Manager to the Project Board at the end of each management stage of the project. This provides information about the project performance during the stage and the project status at stage end. enhance (risk response)A risk response to an opportunity where proactive actions are taken to enhance both the probability of the event occurring and the impact of the event should it occur. event-driven controlA control that takes place when a specific event occurs. This could be, for example, the end of a stage, the completion of the Project Initiation Documentation, or the creation of an Exception Report. It could also include organizational events that may affect the project, such as the end of the financial year. exception A situation where it can be forecast that exceptionA situation where it can be forecast that there will be a deviation beyond the tolerance levels agreed between Project Manager and Project Board (or between Project Board and corporate or programme management). exception assessmentThis is a review by the Project Board to approve (or reject) an Exception Plan. Exception PlanThis is a plan that often follows an Exception Report. For a Stage Plan exception, it covers the period from the present to the end of the current stage. If the exception were at project level, the Project Plan would be replaced. Exception ReportA description of the exception situation, its impact, options, recommendation and impact of the recommendation. This report is prepared by the Project Manager for the Project Board. ExecutiveThe single individual with overall responsibility for ensuring that a project meets its objectives and delivers the projected benefits. This individual should ensure that the project maintains its business focus, that it has clear authority, and that the work, including risks, is actively managed. The Executive is the chair of the Project Board. He or she represents the customer and is responsible for the Business Case. exploit (risk response)A risk response to an opportunity by seizing the opportunity to ensure that it will happen and that the impact will be realized. fallback (risk response)A risk response to a threat by putting in place a fallback plan for the actions that will be taken to reduce the impact of the threat should the risk occur. follow-on action recommendationsRecommended actions related to unfinished work, ongoing issues and risks, and any other activities needed to take a product to the next phase of its life. These are summarized and included in the End Stage Report (for phased handover) and End Project Report. governance (corporate)The ongoing activity of maintaining a sound system of internal control by which the directors and officers of an organization ensure that effective management systems, including financial monitoring and control systems, have been put in place to protect assets, earning capacity and the reputation of the organization. governance (project)Those areas of corporate governance that are specifically related to project activities. Effective governance of project management ensures that an organization's project portfolio is aligned to the organization's objectives, is delivered efficiently and is sustainable. handoverThe transfer of ownership of a set of products to the respective user(s). The set of products is known as a release. There may be more than one handover in the life of a project (phased delivery). The final handover takes place in the Closing a Project process. Highlight ReportA time-driven report from the Project Manager to the Project Board on stage progress. host siteA site where project work is being undertaken (for example, an office or construction site). impact (of risk)The result of a particular threat or opportunity actually occurring, or the anticipation of such a result. inherent riskThe exposure arising from a specific risk before any action has been taken to manage it. initiation stageThe period from when the Project Board authorizes initiation to when they authorize the project (or decide not to go ahead with the project). The detailed planning and establishment of the project management infrastructure is covered by the Initiating a Project process. issueA relevant event that has happened, was not planned, and requires management action. It can be any concern, query, request for change, suggestion or off-specification raised during a project. Project issues can be about anything to do with the project. Issue RegisterA register used to capture and maintain information on all of the issues that are being managed formally. The Issue Register should be monitored by the Project Manager on a regular basis. Issue ReportA report containing the description, impact assessment and recommendations for a request for change, off-specification or a problem/concern. It is only created for those issues that need to be handled formally. Lessons LogAn informal repository for lessons that apply to this project or future projects. Lessons ReportA report that documents any lessons that can be usefully applied to other projects. The purpose of the report is to provoke action so that the positive lessons from a project become embedded in the organization's way of working and that the organization is able to avoid the negative lessons on future projects. logsInformal repositories managed by the Project Manager that do not require any agreement by the Project Board on their format and composition. PRINCE2 has two logs: the Daily Log and the Lessons Log. management productA product that will be required as part of managing the project, and establishing and maintaining quality (for example, Highlight Report, End Stage Report etc.). The management products stay constant, whatever the type of project, and can be used as described, or with any relevant modifications, for all projects. There are three types of management product: baselines, records and reports. management stageThe section of a project that the Project Manager is managing on behalf of the Project Board at any one time, at the end of which the Project Board will wish to review progress to date, the state of the Project Plan, the Business Case and risks, and the next Stage Plan in order to decide whether to continue with the project. milestoneA significant event in a plan's schedule, such as completion of key Work Packages, a technical stage, or a management stage. off-specificationSomething that should be provided by the project, but currently is not (or is forecast not to be) provided. This might be a missing product or a product not meeting its specifications. It is one type of issue. operational and maintenance acceptanceA specific type of acceptance by the person or group who will support the product once it is handed over into the operational environment. outcomeThe result of change, normally affecting real-world behaviour and/or circumstances. Outcomes are desired when a change is conceived. They are achieved as a result of the activities undertaken to effect the change. outputA specialist product that is handed over to a user(s). Note that management products are not outputs but are created solely for the purpose of managing the project. performance targetsA plan's goals for time, cost, quality, scope, benefits and risk. planA detailed proposal for doing or achieving something which specifies the what, when, how and by whom. In PRINCE2 there are only the following types of plan: Project Plan, Stage Plan, Team Plan, Exception Plan and Benefits Review Plan. planned closureThe PRINCE2 activity to close a project. planning horizonThe period of time for which it is possible to accurately plan. portfolioAll the programmes and stand-alone projects being undertaken by an organization, a group of organizations, or an organizational unit. premature closureThe PRINCE2 activity to close a project before its planned closure. The Project Manager must ensure that work in progress is not simply abandoned, but that the project salvages any value created to date, and checks that any gaps left by the cancellation of the project are raised to corporate or programme management. prerequisites (plan)Any fundamental aspects that must be in place, and remain in place, for a plan to succeed. PRINCE2A method that supports some selected aspects of project management. The acronym stands for PRojects IN a Controlled Environment. PRINCE2 principlesThe guiding obligations for good project management practice that form the basis of a project being managed using PRINCE2. PRINCE2 projectA project that applies the PRINCE2 principles. probabilityThis is the evaluated likelihood of a particular threat or opportunity actually happening, including a consideration of the frequency with which this may arise. problem/concernA type of issue (other than a request for change or off-specification) that the Project Manager needs to resolve or escalate. procedureA series of actions for a particular aspect of project management established specifically for the project - for example, a risk management procedure. processA structured set of activities designed to accomplish a specific objective. A process takes one or more defined inputs and turns them into defined outputs. producerThe person or group responsible for developing a product. productAn input or output, whether tangible or intangible, that can be described in advance, created and tested. PRINCE2 has two types of products - management products and specialist products. product breakdown structureA hierarchy of all the products to be produced during a plan. product checklistA list of the major products of a plan, plus key dates in their delivery. Product DescriptionA description of a product's purpose, composition, derivation and quality criteria. It is produced at planning time, as soon as possible after the need for the product is identified. product flow diagramA diagram showing the sequence of production and interdependencies of the products listed in a product breakdown structure. Product Status AccountA report on the status of products. The required products can be specified by identifier or the part of the project in which they were developed. product-based planningA technique leading to a comprehensive plan based on the creation and delivery of required outputs. The technique considers prerequisite products, quality requirements and the dependencies between products. programmeA temporary flexible organization structure created to coordinate, direct and oversee the implementation of a set of related projects and activities in order to deliver outcomes and benefits related to the organization's strategic objectives. A programme is likely to have a life that spans several years. projectA temporary organization that is created for the purpose of delivering one or more business products according to an agreed Business Case. Project ApproachA description of the way in which the work of the project is to be approached. For example, are we building a product from scratch or buying in a product that already exists? Project AssuranceThe Project Board's responsibilities to assure itself that the project is being conducted correctly. The Project Board members each have a specific area of focus for Project Assurance, namely business assurance for the Executive, user assurance for the Senior User(s), and supplier assurance for the Senior Supplier(s). project authorization notificationAdvice from the Project Board to inform all stakeholders and the host sites that the project has been authorized and to request any necessary logistical support (e.g. communication facilities, equipment and any project support) sufficient for the duration of the project. Project BriefStatement that describes the purpose, cost, time and performance requirements, and constraints for a project. It is created pre-project during the Starting up a Project process and is used during the Initiating a Project process to create the Project Initiation Documentation and its components. It is superseded by the Project Initiation Documentation and not maintained. Project Initiation DocumentationA logical set of documents that brings together the key information needed to start the project on a sound basis and that conveys the information to all concerned with the project. project initiation notificationAdvice from the Project Board to inform all stakeholders and the host sites that the project is being initiated and to request any necessary logistical support (e.g. communication facilities, equipment and any project support) sufficient for the initiation stage. project lifecycleThe period from the start-up of a project to the acceptance of the project product. project managementThe planning, delegating, monitoring and control of all aspects of the project, and the motivation of those involved, to achieve the project objectives within the expected performance targets for time, cost, quality, scope, benefits and risks. project management teamThe entire management structure of the Project Board, and Project Manager, plus any Team Manager, Project Assurance and Project Support roles. project management team structureAn organization chart showing the people assigned to the project management team roles to be used, and their delegation and reporting relationships. Project ManagerThe person given the authority and responsibility to manage the project on a day-to-day basis to deliver the required products within the constraints agreed with the Project Board. project mandateAn external product generated by the authority commissioning the project that forms the trigger for Starting up a Project. project officeA temporary office set up to support the delivery of a specific change initiative being delivered as a project. If used, the project office undertakes the responsibility of the Project Support role. Project PlanA high-level plan showing the major products of the project, when they will be delivered and at what cost. An initial Project Plan is presented as part of the Project Initiation Documentation. This is revised as information on actual progress appears. It is a major control document for the Project Board to measure actual progress against expectations. project productWhat the project must deliver in order to gain acceptance. Project Product DescriptionA special type of Product Description used to gain agreement from the user on the project's scope and requirements, to define the customer's quality expectations, and to define the acceptance criteria for the project. Project SupportAn administrative role in the project management team. Project Support can be in the form of advice and help with project management tools, guidance, administrative services such as filing, and the collection of actual data. proximity (of risk)The time factor of risk, i.e. when the risk may occur. The impact of a risk may vary in severity depending on when the risk occurs. qualityThe totality of features and inherent or assigned characteristics of a product, person, process, service and/or system that bears on its ability to show that it meets expectations or satisfies stated needs, requirements or specifications. quality assuranceAn independent check that products will be fit for purpose or meet requirements. quality controlThe process of monitoring specific project results to determine whether they comply with relevant standards and of identifying ways to eliminate causes of unsatisfactory performance. quality criteriaA description of the quality specification that the product must meet, and the quality measurements that will be applied by those inspecting the finished product. quality inspectionA systematic, structured assessment of a product carried out by two or more carefully selected people (the review team) in a planned, documented and organized fashion. quality managementThe coordinated activities to direct and control an organization with regard to quality. Quality Management StrategyA strategy defining the quality techniques and standards to be applied, and the various responsibilities for achieving the required quality levels, during a project. quality management systemThe complete set of quality standards, procedures and responsibilities for a site or organization. In the project context, 'sites' and 'organizations' should be interpreted as the permanent or semi-permanent organization(s) sponsoring the project work, i.e. they are 'external' to the project's temporary organization. A programme, for instance, can be regarded as a semi-permanent organization that sponsors projects - and it may have a documented quality management system. quality recordsEvidence kept to demonstrate that the required quality assurance and quality control activities have been carried out. Quality RegisterA register containing summary details of all planned and completed quality activities. The Quality Register is used by the Project Manager and Project Assurance as part of reviewing progress. quality reviewSee 'quality inspection'. quality review techniqueA quality inspection technique with defined roles and a specific structure. It is designed to assess whether a product that takes the form of a document (or similar, e.g. a presentation) is complete, adheres to standards and meets the quality criteria agreed for it in the relevant Product Description. The participants are drawn from those with the necessary competence to evaluate its fitness for purpose. quality toleranceThe tolerance identified for a product for a quality criterion defining an acceptable range of values. Quality tolerance is documented in the Project Product Description (for the project-level quality tolerance) and in the Product Description for each product to be delivered. recordsDynamic management products that maintain information regarding project progress. reduce (risk response)A response to a risk where proactive actions are taken to reduce the probability of the event occurring by performing some form of control, and/or to reduce the impact of the event should it occur. registersFormal repositories managed by the Project Manager that require agreement by the Project Board on their format, composition and use. PRINCE2 has three registers: Issue Register, Risk Register and Quality Register. reject (risk response)A response to a risk (opportunity) where a conscious and deliberate decision is taken not to exploit or enhance an opportunity, having discerned that it is more economical to do so than to attempt a risk response action. The opportunity should continue to be monitored. releaseThe set of products in a handover. The contents of a release are managed, tested and deployed as a single entity. See also 'handover'. reportsManagement products providing a snapshot of the status of certain aspects of the project. request for changeA proposal for a change to a baseline. It is a type of issue. residual riskThe risk remaining after the risk response has been applied. responsible authorityThe person or group commissioning the project (typically corporate or programme management) who has the authority to commit resources and funds on behalf of the commissioning organization. reviewerA person or group independent of the producer who assesses whether a product meets its requirements as defined in its Product Description. riskAn uncertain event or set of events that, should it occur, will have an effect on the achievement of objectives. A risk is measured by a combination of the probability of a perceived threat or opportunity occurring, and the magnitude of its impact on objectives. risk actioneeA nominated owner of an action to address a risk. Some actions may not be within the remit of the Risk Owner to control explicitly; in that situation there should be a nominated owner of the action to address the risk. He or she will need to keep the risk owner apprised of the situation. risk appetiteAn organization's unique attitude towards risk taking that in turn dictates the amount of risk that it considers is acceptable. risk estimationThe estimation of probability and impact of an individual risk, taking into account predetermined standards, target risk levels, interdependencies and other relevant factors. risk evaluationThe process of understanding the net effect of the identified threats and opportunities on an activity when aggregated together. risk managementThe systematic application of principles, approaches and processes to the tasks of identifying and assessing risks, and then planning and implementing risk responses. Risk Management StrategyA strategy describing the goals of applying risk management, as well as the procedure that will be adopted, roles and responsibilities, risk tolerances, the timing of risk management interventions, the tools and techniques that will be used, and the reporting requirements. risk ownerA named individual who is responsible for the management, monitoring and control of all aspects of a particular risk assigned to them, including the implementation of the selected responses to address the threats or to maximize the opportunities. risk profileA description of the types of risk that are faced by an organization and its exposure to those risks. Risk RegisterA record of identified risks relating to an initiative, including their status and history. risk responseActions that may be taken to bring a situation to a level where exposure to risk is acceptable to the organization. These responses fall into a number of risk response categories. risk response categoryA category of risk response. For threats, the individual risk response category can be avoid, reduce, transfer, accept or share. For opportunities, the individual risk response category can be exploit, enhance, reject or share. risk toleranceThe threshold levels of risk exposure which, when exceeded, will trigger an Exception Report to bring the situation to the attention of the Project Board. Risk tolerances could include limits on the plan's aggregated risks (e.g. cost of aggregated threats to remain less than 10% of the plan's budget), or limits on any individual threat (e.g. any threat to operational service). Risk tolerance is documented in the Risk Management Strategy. risk tolerance lineA line drawn on the summary risk profile. Risks that appear above this line cannot be accepted (lived with) without referring them to a higher authority. For a project, the Project Manager would refer these risks to the Project Board. role descriptionA description of the set of responsibilities specific to a role. scheduleGraphical representation of a plan (for example, a Gantt chart), typically describing a sequence of tasks, together with resource allocations, which collectively deliver the plan. In PRINCE2, project activities should only be documented in the schedules associated with a Project Plan, Stage Plan or Team Plan. Actions that are allocated from day-to-day management may be documented in the relevant project log (i.e. Risk Register, Daily Log, Issue Register, Quality Register) if they do not require significant activity. scopeFor a plan, the sum total of its products and the extent of their requirements. It is described by the product breakdown structure for the plan and associated Product Descriptions. scope toleranceThe permissible deviation in a plan's scope that is allowed before the deviation needs to be escalated to the next level of management. Scope tolerance is documented in the respective plan in the form of a note or reference to the product breakdown structure for that plan. See 'tolerance'. Senior Responsible OwnerA UK government term for the individual responsible for ensuring that a project or programme of change meets its objectives and delivers the projected benefits. The person should be the owner of the overall business change that is being supported by the project. The Senior Responsible Owner (SRO) should ensure that the change maintains its business focus, that it has clear authority, and that the context, including risks, is actively managed. This individual must be senior and must take personal responsibility for successful delivery of the project. The SRO should be recognized as the owner throughout the organization. The SRO appoints the project's Executive (or in some cases may elect to be the Executive). Senior SupplierThe Project Board role that provides knowledge and experience of the main discipline(s) involved in the production of the project's deliverable(s). The Senior Supplier represents the supplier interests within the project and provides supplier resources. Senior UserThe Project Board role accountable for ensuring that user needs are specified correctly and that the solution meets those needs. share (risk response)A risk response to either a threat or an opportunity through the application of a pain/gain formula: both parties share the gain (within pre-agreed limits) if the cost is less than the cost plan; and both share the pain (again within pre-agreed limits) if the cost plan is exceeded. specialist productA product whose development is the subject of the plan. The specialist products are specific to an individual project (for example, an advertising campaign, a car park ticketing system, foundations for a building, a new business process etc.) Also known as a deliverable or output. sponsorThe main driving force behind a programme or project. PRINCE2 does not define a role for the sponsor, but the sponsor is most likely to be the Executive on the Project Board, or the person who has appointed the Executive. stageSee 'management stage' or 'technical stage'. Stage PlanA detailed plan used as the basis for project management control throughout a stage. stakeholderAny individual, group or organization that can affect, be affected by, or perceive itself to be affected by, an initiative (programme, project, activity, risk). start-upThe pre-project activities undertaken by the Executive and the Project Manager to produce the outline Business Case, Project Brief and Initiation Stage Plan. strategyAn approach or line to take, designed to achieve a long-term aim. Strategies can exist at different levels - at the corporate, programme and project level. At the project level, PRINCE2 defines four strategies: Communication Management Strategy, Configuration Management Strategy, Quality Management Strategy and Risk Management Strategy. supplierThe person, group or groups responsible for the supply of the project's specialist products. tailoringThe appropriate use of PRINCE2 on any given project, ensuring that there is the correct amount of planning, control, governance and use of the processes and themes (whereas the adoption of PRINCE2 across an organization is known as 'embedding'). Team ManagerThe person responsible for the production of those products allocated by the Project Manager (as defined in a Work Package) to an appropriate quality, timescale and at a cost acceptable to the Project Board. This role reports to, and takes direction from, the Project Manager. If a Team Manager is not assigned, then the Project Manager undertakes the responsibilities of the Team Manager role. Team PlanAn optional level of plan used as the basis for team management control when executing Work Packages. technical stageA method of grouping work together by the set of techniques used, or the products created. This results in stages covering elements such as design, build and implementation. Such stages are technical stages and are a separate concept from management stages. themeAn aspect of project management that needs to be continually addressed, and that requires specific treatment for the PRINCE2 processes to be effective. time toleranceThe permissible deviation in a plan's time that is allowed before the deviation needs to be escalated to the next level of management. Time tolerance is documented in the respective plan. See also 'tolerance'. time-driven controlA management control that is periodic in nature, to enable the next higher authority to monitor progress - e.g. a control that takes place every two weeks. PRINCE2 offers two key time-driven progress reports: Checkpoint Report and Highlight Report. toleranceThe permissible deviation above and below a plan's target for time and cost without escalating the deviation to the next level of management. There may also be tolerance levels for quality, scope, benefit and risk. Tolerance is applied at project, stage and team levels. trancheA programme management term describing a group of projects structured around distinct step changes in capability and benefit delivery. transfer (risk response)A response to a threat where a third party takes on responsibility for some of the financial impact of the threat (for example, through insurance or by means of appropriate clauses in a contract). triggerAn event or decision that triggers a PRINCE2 process. user acceptanceA specific type of acceptance by the person or group who will use the product once it is handed over into the operational environment. userThe person or group who will use one or more of the project's products. variantA variation on a baselined product. For example, an operations manual may have an English variant and a Spanish variant. versionA specific baseline of a product. Versions typically use naming conventions that enable the sequence or date of the baseline to be identified. For example, Project Plan version 2 is the baseline after Project Plan version 1. waterfall methodA development approach that is linear and sequential with distinct goals for each phase of development. Once a phase of development is completed, the development proceeds to the next phase and earlier phases are not revisited (hence the analogy that water flowing down a mountain cannot go back). Work PackageThe set of information relevant to the creation of one or more products. It will contain a description of the work, the Product Description(s), details of any constraints on production, and confirmation of the agreement between the Project Manager and the person or Team Manager who is to implement the Work Package that the work can be done within the constraints. | ||||||||||||||||||||||||||
10. Continued Improvement & Feedback | ||||||||||||||||||||||||||
Continual improvement of the project management standards and guidance can be achieved through the development of this Techniques Guide with information on best practice, lessons learned and hints and tips.
To help you to provide input to the guidance, you should create and maintain a Lessons Log. This log should be used to record events, actions and techniques that assisted or enhanced the project; and those that did not. At project closure, lessons should be disseminated and passed to the Project Management Office. General feedback on the Project Management Guides should be sent to the Project Management Office. Lessons Reports should be available centrally in order to benefit future projects. Electronic project files available to all PM's and Project Boards would allow continuous improvement on project performance. |
Back to top | Previous | Next